Rock District Solar
20 MW generation in Schoharie, NY · In queue since July 2016 · Proposed COD February 2027
20 MW
Capacity
1
Components
Solar
9y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
Rock District Solar is a proposed 20 MW solar generation project located in Schoharie County, New York. Developed by Rock District Solar, LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-564, filed on July 25, 2016. The proposed commercial operation date is February 1, 2027. Its interconnection status is currently in the Facility Study phase, with point of interconnection at the Sharon - Cobleskill 69kV line.
The project consists of 20 MW of solar photovoltaic generation. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Schoharie
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Rock District Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Sharon - Cobleskill 69kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- HIGH
- POI Substation
- Sharon
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rock District Solar