Tayandenega Solar
20 MW generation in Montgomery, NY · In queue since July 2016 · Proposed COD February 2027
20 MW
Capacity
1
Components
Solar
9y 10m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-01
The Tayandenega Solar project is a proposed 20 MW solar generation project located in Montgomery County, New York. Developed by Tayandenega Solar, LLC, the project is interconnected to the NYISO grid at the St. Johnsville - Inghams 115kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-565 on July 25, 2016, and has a proposed commercial operation date of February 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 20 MW of solar photovoltaic generation capacity. It is listed as an active project within the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Tayandenega Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
St. Johnsville - Inghams 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tayandenega Solar