Heritage Wind
200.1 MW generation in Genesee, NY · In queue since September 2016 · Proposed COD September 2026
200.1 MW
Capacity
1
Components
Wind
9y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
10 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
Heritage Wind, a proposed wind generation project in Genesee County, New York, is being developed by Heritage Wind, LLC. The project, with a total capacity of 200.1 MW, is currently active in the NYISO interconnection queue as queue ID NYISO-571. The project entered the queue on September 1, 2016, and has a proposed commercial operation date of September 1, 2026. Its interconnection status is currently in the Facility Study phase.
The proposed project interconnects at the Lockport - Mortimer 115kV point of interconnection. Heritage Wind has been the subject of recent news coverage, with 14 articles appearing in the press, primarily focusing on regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Genesee
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Heritage Wind, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Lockport - Mortimer 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26