Watkins Rd Solar
20 MW generation in Herkimer, NY · In queue since November 2016 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
9y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
9y 8m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
Watkins Rd Solar is a proposed 20 MW solar generation project located in Herkimer County, New York. The developer is SunEast Watkins Road Solar LLC. This project is listed in the NYISO interconnection queue as queue ID NYISO-586, with an entry date of November 8, 2016, and a proposed commercial operation date of July 1, 2026. Its interconnection status is currently in the Facility Study phase.
The project is linked to the existing SunEast Watkins Road Solar Project operating plant (EIA ID 62896). The point of interconnection is the Watkins Rd - Ilion 115kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Herkimer
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Watkins Road Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Watkins Rd - Ilion 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone E
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 23567
- POI Substation
- INDECK___ILION