Highview Solar
20 MW generation in Wyoming, NY · In queue since December 2016 · Proposed COD February 2025
20 MW
Capacity
1
Components
Solar
9y 5m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
8y 2m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
Highview Solar is a proposed 20 MW solar generation project located in Wyoming County, New York. The project, developed by SunEast Highview Solar LLC, is in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-591, with an entry date of December 2, 2016. The proposed commercial operation date is February 1, 2025, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing SunEast Highview Solar Project operating plant (EIA ID 63866). The point of interconnection is the South Perry 34.5kV substation, and the interconnecting utility is NYSEG. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Wyoming
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Highview Solar LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
South Perry 34.5kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Highview Solar