Flint Mine Solar (NYISO-637) — Project Summary

Queue ID
NYISO-637
Capacity
100 MW
Technology
Solar
Status
active
Location
Greene, NY
Region
NYISO
Developer
Flint Mine Solar LLC
IA Status
Facility Study

Flint Mine Solar

NYISO-637BetaActiveSolarNYISOLBNL

100 MW generation in Greene, NY · In queue since June 2017 · Proposed COD May 2026

100 MW

Capacity

1

Components

Solar

8y 11m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

8y 11m

Schedule

0 months past proposed COD

Facilities Study50%
Queue EntryJun 29, 2017

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-01

About

Flint Mine Solar is a proposed 100 MW solar generation project located in Greene County, New York. The developer is Flint Mine Solar LLC. This project is listed in the NYISO interconnection queue as queue ID NYISO-637, with an entry date of June 29, 2017, and a proposed commercial operation date of May 1, 2026. Its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Flint Mine Solar operating plant (EIA ID 67090). Recent news coverage indicates activity related to the project in both regulatory and industry contexts.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Greene

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Flint Mine Solar LLC

Utility

NM-NG

Entity

NYISO

Service Type

Point of Interconnection

LaFarge - Pleasant Valley 115kV, Feura Bush - North Catskill 115kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
NYISO Zone F
Hub Confidence
MEDIUM
Nearest Node (Estimated)
23668
POI Substation
ATHENS_STG_1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.