SunEast Skyline Solar LLC
20 MW generation in Oneida, NY · In queue since September 2017 · Proposed COD April 2028
20 MW
Capacity
1
Components
Solar
8y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
SunEast Skyline Solar LLC is a proposed 20 MW solar generation project located in Oneida County, New York. The project, developed by SunEast Skyline Solar LLC, is interconnected within the New York Independent System Operator (NYISO) queue as project number NYISO-670. It entered the queue on September 21, 2017, and has a proposed commercial operation date of April 1, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to the existing SunEast Skyline Solar Project operating plant (EIA ID 62816). Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
NY
County
Oneida
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Skyline Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Campus Rd - Clinton 46kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone E
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.