KCE NY 2
200 MW storage in Montgomery, NY · In queue since January 2018 · Proposed COD June 2027
200 MW
Capacity
1
Components
Battery
8y 4m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
KCE NY 2 is a proposed 200 MW battery storage project located in Montgomery County, New York. The project, developed by KCE NY 2, LLC, is interconnected to the Central Hudson Gas & Electric (CHG&E) system. It is currently in the System Impact Study phase of the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-683, with an original queue entry date of January 18, 2018. The proposed commercial operation date is June 1, 2027.
The KCE NY 2 project has been the subject of recent news coverage, particularly regarding regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 2, LLC
Utility
CHG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Coldenham 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14