Bear Ridge Solar (NYISO-704) — Project Summary

Queue ID
NYISO-704
Capacity
100 MW
Technology
Solar
Status
active
Location
Niagara, NY
Region
NYISO
Developer
Bear Ridge Solar, LLC
IA Status
System Impact Study

Bear Ridge Solar

NYISO-704BetaActiveSolarNYISOLBNL

100 MW generation in Niagara, NY · In queue since March 2018 · Proposed COD April 2027

100 MW

Capacity

1

Components

Solar

8y 2m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection

Total Duration

9y 1m

Impact Study25%
Queue EntryMar 20, 2018

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-01

About

Bear Ridge Solar is a proposed 100 MW solar generation project located in Niagara County, New York. The project, developed by Bear Ridge Solar, LLC, is interconnected to the NYISO queue under queue ID NYISO-704. The project entered the queue on March 20, 2018, and has a proposed commercial operation date of April 1, 2027. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Mountain-Lockport 115kV line.

The proposed project is linked to the existing Bear Ridge operating plant (EIA plant ID 67650). Recent news coverage indicates the project has been featured in eight news articles, primarily focusing on industry and regulatory topics.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Niagara

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Bear Ridge Solar, LLC

Utility

NM-NG

Entity

NYISO

Service Type

Point of Interconnection

Mountain- Lockport 115kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
NYISO Zone A
Hub Confidence
MEDIUM
Nearest Node (Estimated)
24167
POI Substation
MODEL_CITY_ENERGY

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Bear Ridge Solar