High Bridge Wind
100.8 MW generation in Chenango, NY · In queue since April 2018 · Proposed COD February 2025
100.8 MW
Capacity
1
Components
Wind
8y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
6y 10m
Schedule
15 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-02-01
High Bridge Wind is a proposed wind generation project located in Chenango County, New York. The project, developed by High Bridge Wind, LLC, has a total capacity of 100.8 MW. It is interconnected to the NYSEG utility via the E. Norwich - Jennison 115kV point of interconnection.
The project is listed in the NYISO interconnection queue as entry NYISO-706, with a queue entry date of April 25, 2018. Its proposed commercial operation date is February 1, 2025, and its interconnection status is currently in the System Impact Study phase. The project is linked to the existing High Bridge Wind Project operating plant (EIA ID 62894). The High Bridge Wind project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Chenango
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
High Bridge Wind, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
E. Norwich - Jennison 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone E
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about High Bridge Wind