Moraine Solar Energy Center
93.5 MW generation in Allegany, NY · In queue since June 2018 · Proposed COD October 2027
93.5 MW
Capacity
1
Components
Solar
7y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
9y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
The Moraine Solar Energy Center is a proposed 93.5 MW solar generation project located in Allegany County, New York. Developed by EDF Renewables Development, Inc., the project is interconnected to the New York State Electric and Gas (NYSEG) utility via the Moraine 115kV point of interconnection. It is currently listed as active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-716, with an entry date of June 4, 2018.
The proposed commercial operation date for the Moraine Solar Energy Center is October 1, 2027. The project's interconnection status is currently in the System Impact Study phase. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Allegany
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Moraine 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- HIGH
- POI Substation
- Moraine Road Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Moraine Solar Energy Center