Ticonderoga Solar
20 MW generation in Essex, NY · In queue since June 2018 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
7y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
6y 9m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The Ticonderoga Solar project is a proposed 20 MW solar generation facility located in Essex County, New York. The project is being developed by ELP Ticonderoga Solar LLC and is interconnected within the New York Independent System Operator (NYISO) region. It entered the NYISO interconnection queue as queue ID NYISO-734 on June 12, 2018, and has a proposed commercial operation date of March 1, 2025. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 20 MW of solar photovoltaic generation. The point of interconnection is the Ticonderoga 115kV - Republic Line 2. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Essex
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ELP Ticonderoga Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Ticonderoga 115kV - Republic Line 2
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Ticonderoga Solar