Sunrise Wind
880 MW generation in Suffolk, NY · In queue since September 2018 · Proposed COD March 2026
880 MW
Capacity
1
Components
Offshore Wind
7y 8m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
7y 6m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-01
Sunrise Wind is a proposed 880 MW offshore wind generation project located in Suffolk County, New York. The project, developed by Sunrise Wind LLC, is interconnected to the NYISO grid under queue ID NYISO-766. The project entered the interconnection queue on September 28, 2018, and has a proposed commercial operation date of March 1, 2026. Its interconnection status is currently in the System Impact Study phase, and it will connect to the grid at Holbrook 138kV & West Bus 138kV.
The Sunrise Wind project has been the subject of recent news coverage, with 92 articles appearing in the press. These articles primarily focus on industry and development aspects of the project, with some coverage of regulatory and grid-related issues.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Sunrise Wind LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Holbrook 138kV & West Bus 138kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NGRID_A4_DSASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26