Tracy Solar Energy Centre
119 MW generation in Jefferson, NY · In queue since October 2018 · Proposed COD November 2028
119 MW
Capacity
1
Components
Solar
7y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The Tracy Solar Energy Centre is a proposed 119 MW solar generation project located in Jefferson County, New York. Developed by EDF Renewables Development, Inc., the project is interconnected to the NYISO grid under queue ID NYISO-774, with an interconnection queue entry date of October 18, 2018. The proposed commercial operation date is November 1, 2028. The project's interconnection status is currently in the System Impact Study phase.
The Tracy Solar Energy Centre is linked to the existing Tracy Solar Energy Center operating plant (EIA plant ID 65051). Recent news coverage of the project includes regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Jefferson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Thousand Island - Lyme 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone D
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tracy Solar Energy Centre