Levy Grid, LLC
150 MW storage in Erie, NY · In queue since December 2018 · Proposed COD August 2025
150 MW
Capacity
1
Components
Battery
7y 5m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
6y 8m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-08-01
Levy Grid, LLC is a proposed 150 MW battery storage project located in Erie County, New York. The development project, sponsored by Levy Grid, LLC, is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-787. The project entered the queue on December 20, 2018, and has a proposed commercial operation date of August 1, 2025. Its interconnection status is currently in the System Impact Study phase. The project has been mentioned in recent news coverage.
The proposed project consists of 150 MW of battery storage capacity. The point of interconnection is the Gardenville Substation 115kV.
Generated from interconnection queue and public data sources
State
NY
County
Erie
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Levy Grid, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Gardenville Subsation 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BETHLEHEM___STEEL
- POI Substation
- Gardenville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Levy Grid, LLC