Bayonne Energy Center III
49.8 MW storage in Kings, NY · In queue since April 2019 · Proposed COD September 2026
49.8 MW
Capacity
1
Components
Battery
7y 1m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
7y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
The Bayonne Energy Center III project is a proposed 49.8 MW battery storage project located in Kings County, New York. The project, developed by Bayonne Energy Center, is currently in the NYISO interconnection queue as entry NYISO-815, with a queue entry date of April 5, 2019. The proposed commercial operation date is September 1, 2026.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Gowanus 345kV substation. The project is linked to an existing operating plant and has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Bayonne Energy Center
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Gowanus 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GOWANUS_GT2_1
- POI Substation
- Gowanus Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Bayonne Energy Center III