Luyster Creek Energy Storage 1
57.3 MW storage in Queens, NY · In queue since May 2019 · Proposed COD May 2026
57.3 MW
Capacity
1
Components
Battery
7 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
7 years
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
Luyster Creek Energy Storage 1 is a proposed 57.3 MW battery storage project located in Queens County, New York. The project, being developed by Astoria Generating Company, LP, is interconnected to the ConEd utility via the Astoria West 138kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-835 on May 7, 2019, and has a proposed commercial operation date of May 1, 2026. The project's interconnection status is currently in the System Impact Study phase.
The Luyster Creek Energy Storage 1 project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Queens
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Astoria Generating Company, LP
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Astoria West 138kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NGRID_A4_DSASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Luyster Creek Energy Storage 1