Fairway Solar
20 MW generation in St. Lawrence, NY · In queue since May 2019 · Proposed COD March 2025
20 MW
Capacity
1
Components
Solar
7 years
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
5y 10m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The Fairway Solar project is a proposed 20 MW solar generation facility located in St. Lawrence County, New York. The project, developed by SunEast Fairway Solar LLC, is currently active in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-848. It entered the queue on May 20, 2019, and has a proposed commercial operation date of March 1, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the McIntyre - Corning 115kV line (#6). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
St. Lawrence
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Fairway Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
McIntyre - Corning 115kV (Line#6)
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fairway Solar