Riverside Solar
100 MW generation in Jefferson, NY · In queue since June 2019 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
6y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Riverside Solar is a proposed 100 MW solar generation project located in Jefferson County, New York. Developed by Riverside Solar, LLC, the project is interconnected to the NYISO grid at the Lyme Substation 115kV. It entered the NYISO interconnection queue as queue ID NYISO-882 on June 10, 2019.
The proposed commercial operation date (COD) for Riverside Solar is December 1, 2027. The project's interconnection status is currently in the System Impact Study phase. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NY
County
Jefferson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Riverside Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Lyme Substation 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM