Astoria BES to 27kV North Queens
15 MW storage in Queens, NY · In queue since October 2019 · Proposed COD December 2025
15 MW
Capacity
1
Components
Battery
6y 7m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
6y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
The Astoria BES to 27kV North Queens project is a proposed 15 MW battery storage project located in Queens County, New York. Developed by Astoria Generating Company, LP, the project is interconnected to the ConEd utility and participates in the NYISO interconnection queue as queue ID NYISO-930. The project entered the queue on October 25, 2019, and has a proposed commercial operation date of December 1, 2025. Its interconnection status is currently in the Facility Study phase.
The development project consists of a single 15 MW battery component. The point of interconnection is the North Queens 27kV substation. The project is listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Queens
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Astoria Generating Company, LP
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
North Queens 27kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- POLETTI____
- POI Substation
- North Queens Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Astoria BES to 27kV North Queens