20 MW generation in Livingston, NY · In queue since October 2019 · Proposed COD May 2025
20 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
5y 7m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-05-01
Hatchery Solar is a proposed 20 MW solar generation project located in Livingston County, New York. The project, developed by Hatchery Solar LLC, is interconnected within the New York Independent System Operator (NYISO) queue as project number NYISO-932. It entered the queue on October 29, 2019, and has a proposed commercial operation date of May 1, 2025. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Hatchery Solar operating plant (EIA ID 65901). Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Livingston
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Hatchery Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Caledonia - Golah 34.5 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- NYISO Zone B
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 24207
- POI Substation
- NEG___GEN_MONROE
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hatchery Solar