Sugar Maple Solar
125 MW generation in Lewis, NY · In queue since December 2019 · Proposed COD December 2027
125 MW
Capacity
1
Components
Solar
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Sugar Maple Solar is a proposed 125 MW solar generation project located in Lewis County, New York. The project, developed by Sugar Maple Solar, LLC, is currently active in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-953. The project entered the queue on December 5, 2019, and has a proposed commercial operation date of December 1, 2027. Its interconnection status is currently in the System Impact Study phase.
The point of interconnection for the project is the North Carthage - Taylorville #8 and Black River - Taylorville #2 115kV lines. The Sugar Maple Solar project has been mentioned in recent news coverage related to development.
Generated from interconnection queue and public data sources
State
NY
County
Lewis
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Sugar Maple Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
North Carthage - Taylorville #8 and Black River - Taylorville #2 115kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NORTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.