KCE NY 5
94 MW storage in Ulster, NY · In queue since December 2019 · Proposed COD December 2027
94 MW
Capacity
1
Components
Battery
6y 5m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
8 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
KCE NY 5 is a proposed 94 MW battery storage project located in Ulster County, New York. Developed by KCE NY 5 LLC, the project is interconnected to Central Hudson Gas & Electric (CHG&E) via the Ohioville 115 kV point of interconnection. The project is currently in the System Impact Study phase of the NYISO interconnection queue, having entered the queue on December 27, 2019, under queue ID NYISO-967. The proposed commercial operation date is December 1, 2027.
The KCE NY 5 project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Ulster
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 5 LLC
Utility
CHG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Ohioville 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- POI Substation
- Ohioville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesNo ask pi reports yet for this entity.