ATLANTIC SHORES OFFSHORE WIND PROJECT 3
1,400 MW generation in Kings, NY · In queue since August 2024 · Proposed COD December 2033
1,400 MW
Capacity
1
Components
Offshore Wind
1y 9m
In Queue
—
IA Status
COD target: 2033
Total Duration
9y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-12-01
The Atlantic Shores Offshore Wind Project 3 is a proposed 1400 MW offshore wind generation project located in Kings County, New York. Developed by Atlantic Shores Offshore Wind LLC, the project is interconnected to the ConEd utility via the Brooklyn Clean Energy Hub 345kV point of interconnection.
The project is listed in the NYISO interconnection queue as entry C24-011, with a queue entry date of August 1, 2024, and a proposed commercial operation date of December 1, 2033. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ATLANTIC SHORES OFFSHORE WIND LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
BROOKLYN CLEAN ENERGY HUB 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- POI Substation
- BROOKLYN