Roma Storage
150 MW storage in Queens, NY · In queue since August 2024 · Proposed COD August 2028
150 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
Roma Storage is a proposed 150 MW battery storage project located in Queens County, New York. The development project, sponsored by Roma Storage, is interconnected to the ConEd utility grid at the Astoria East 138 kV point of interconnection. It is currently active in the NYISO interconnection queue under queue ID NYISO-C24-014, having entered the queue on August 1, 2024, with a proposed commercial operation date of August 1, 2028.
The Roma Storage project consists of 150 MW of battery storage capacity. The project has been the subject of recent news coverage, with four articles appearing in industry and deals publications.
Generated from interconnection queue and public data sources
State
NY
County
Queens
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Roma Storage
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Astoria East 138 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.