Salt Rush Wind Energy
150 MW generation in Wyoming, NY · In queue since August 2024 · Proposed COD November 2029
150 MW
Capacity
1
Components
Wind
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-01
Salt Rush Wind Energy is a proposed 150 MW wind energy project located in Wyoming County, New York. The project, developed by Salt Rush Wind Energy LLC, is interconnected to the NYSEG utility via the Stony Creek 230 kV point of interconnection. Designated as queue ID NYISO-C24-016 within the NYISO interconnection queue, the project entered the queue on August 1, 2024, with a proposed commercial operation date of November 1, 2029.
The Salt Rush Wind Energy project is currently listed as active in the interconnection queue. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
NY
County
Wyoming
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Salt Rush Wind Energy LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Stony Creek 230 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ORANGEVILLE___ESR
- POI Substation
- Stony Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.