Bluepoint Wind 1
1,310 MW generation in Kings, NY · In queue since August 2024 · Proposed COD December 2032
1,310 MW
Capacity
1
Components
Offshore Wind
1y 9m
In Queue
—
IA Status
COD target: 2032
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-12-01
Bluepoint Wind 1 is a proposed 1310 MW offshore wind generation project located in Kings County, New York. The project, being developed by Bluepoint Wind LLC, is interconnected to the NYISO queue under queue ID NYISO-C24-021. The point of interconnection is the Brooklyn Clean Energy Hub 345kV Substation, with utility Consolidated Edison (CONED) as the transmission provider. The project entered the queue on August 1, 2024, with a proposed commercial operation date of December 1, 2032.
The proposed project is currently listed as active in the NYISO interconnection queue. It has been the subject of recent news coverage, with five articles categorized as pertaining to industry and regulatory matters.
Generated from interconnection queue and public data sources
State
NY
County
Kings
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Bluepoint Wind LLC
Utility
CONED
Entity
NYISO
Service Type
—
Point of Interconnection
Brooklyn Clean Energy Hub 345kV Substation
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- POI Substation
- BROOKLYN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26