KCE NY 26
60 MW storage in Suffolk, NY · In queue since August 2024 · Proposed COD January 2028
60 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
KCE NY 26 is a proposed 60 MW battery storage project located in Suffolk County, New York. The project, developed by KCE NY 26, LLC, is interconnected with the Long Island Power Authority (LIPA) and is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-023. The project entered the queue on August 1, 2024, with a proposed commercial operation date of January 1, 2028.
The project consists of 60 MW of battery storage. The point of interconnection (POI) is the Jamesport - Peconic 69kV line. The project is currently listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Suffolk
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 26, LLC
Utility
LIPA
Entity
NYISO
Service Type
—
Point of Interconnection
Jamesport - Peconic 69kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE K
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about KCE NY 26