KCE NY 32
79 MW storage in Orange, NY · In queue since August 2024 · Proposed COD January 2028
79 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
The KCE NY 32 project is a proposed 79 MW battery storage project located in Orange County, New York. Developed by KCE NY 32, LLC, the project consists of 79 MW of battery capacity. It is currently active in the NYISO interconnection queue as entry NYISO-C24-025, with a queue entry date of August 1, 2024, and a proposed commercial operation date of January 1, 2028.
The project is interconnected to the O&R utility at the Cuddebackville 69 kV point of interconnection. As of the latest data, the project does not have an executed Interconnection Agreement. The project has appeared in recent news coverage regarding energy storage development in New York.
Generated from interconnection queue and public data sources
State
NY
County
Orange
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 32, LLC
Utility
O&R
Entity
NYISO
Service Type
—
Point of Interconnection
Cuddebackville 69 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about KCE NY 32