Taproot Solar
185 MW generation in Montgomery, NY · In queue since August 2024 · Proposed COD July 2029
185 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
Taproot Solar is a proposed 185 MW solar generation project located in Montgomery County, New York. The project, developed by Taproot Solar LLC, is interconnected to the NYISO grid at the Edic - Princetown 345 kV, Line #351 point of interconnection. It entered the NYISO interconnection queue as project NYISO-C24-026 on August 1, 2024, and has a proposed commercial operation date of July 1, 2029.
The project is currently listed as active in the interconnection queue. Utility LSPower is also associated with the project. The Taproot Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Taproot Solar LLC
Utility
LSPower
Entity
NYISO
Service Type
—
Point of Interconnection
Edic - Princetown 345 kV, Line #351
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.