Crossbuck Energy Storage, LLC
100 MW storage in Greene, NY · In queue since August 2024 · Proposed COD May 2028
100 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The Crossbuck Energy Storage, LLC project is a proposed 100 MW battery storage development in Greene County, New York. Developed by BayWa r.e Solar Projects LLC, the project is interconnected to the Central Hudson Gas & Electric (CHGE) grid at the Coxsackie 69 kV substation.
The project is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-031, with a queue entry date of August 1, 2024, and a proposed commercial operation date of May 1, 2028. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Greene
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BayWa r.e Solar Projects LLC
Utility
CHGE
Entity
NYISO
Service Type
—
Point of Interconnection
Coxsackie 69 kV substation
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Crossbuck Energy Storage, LLC