Vestal Battery Storage
110 MW storage in Broome, NY · In queue since August 2024 · Proposed COD May 2028
110 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The Vestal Battery Storage project is a proposed 110 MW battery storage project located in Broome County, New York. The project, being developed by BayWa r.e. Solar Projects LLC, is interconnected to the New York Independent System Operator (NYISO) via the Castle Garden - Jones 115 kV point of interconnection.
The project is listed in the NYISO interconnection queue as entry NYISO-C24-041, with an original queue entry date of August 1, 2024. The proposed commercial operation date is May 1, 2028. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
NY
County
Broome
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BayWa r.e. Solar Projects LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Castle Garden - Jones 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.