Robinson Hill BESS
1,117 MW storage in Broome, NY · In queue since August 2024 · Proposed COD October 2027
1,117 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
The Robinson Hill BESS is a proposed 1117 MW battery storage project located in Broome County, New York. Developed by Oakdale BESS, the project is interconnected to the NYISO grid at the Oakdale 345kV Substation. It entered the NYISO interconnection queue as project number C24-046 on August 1, 2024, and has a proposed commercial operation date of October 1, 2027.
The Robinson Hill BESS project is currently listed as active in the NYISO interconnection queue. The project is to be connected to the New York State Electric and Gas (NYSEG) distribution network. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Broome
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Oakdale BESS
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Oakdale 345kv Substation
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Oakdale Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Robinson Hill BESS