Lincoln Park DG, LLC
150 MW storage in Ulster, NY · In queue since August 2024 · Proposed COD May 2028
150 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The Lincoln Park DG, LLC project is a proposed 150 MW battery storage project located in Ulster County, New York. Developed by BayWa r.e. Solar Projects LLC, the project consists of a single 150 MW battery component. It is currently active in the NYISO interconnection queue as entry NYISO-C24-047, with a queue entry date of August 1, 2024.
The proposed commercial operation date for the Lincoln Park DG, LLC project is May 1, 2028. The point of interconnection is the Lincoln Park - East Kingston 115 kV substation. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
NY
County
Ulster
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BayWa r.e. Solar Projects LLC
Utility
CHGE
Entity
NYISO
Service Type
—
Point of Interconnection
Lincoln Park - East Kingston 115 kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- POI Substation
- Lincoln