BPP NY Lansing BESS I
200 MW storage in Tompkins, NY · In queue since August 2024 · Proposed COD December 2026
200 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The BPP NY Lansing BESS I project is a proposed 200 MW battery storage project located in Tompkins County, New York. The developer is BPP NY Lansing BESS I LLC, and the project is interconnected with NYSEG. It is listed in the NYISO interconnection queue as entry NYISO-C24-048, with a queue entry date of August 1, 2024, and a proposed commercial operation date of December 1, 2026.
The project is currently listed as active in the interconnection queue. The point of interconnection is the Milliken 115kV substation, also known as Cayuga 115kV. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Tompkins
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BPP NY Lansing BESS I LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Milliken 115kV (aka Cayuga 115kV)
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BPP NY Lansing BESS I