North Catskill DG LLC
100 MW storage in Greene, NY · In queue since August 2024 · Proposed COD May 2028
100 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
North Catskill DG LLC is a proposed 100 MW battery storage project located in Greene County, New York. The project, being developed by BayWa r.e Solar Projects LLC, is interconnected to the Central Hudson Gas & Electric (CHGE) grid at the North Catskill -Churchtown 115 kV point of interconnection. It is listed in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-C24-049, with an original queue entry date of August 1, 2024.
The proposed commercial operation date (COD) for the North Catskill DG LLC project is May 1, 2028. The project's interconnection status is currently listed as active within the NYISO queue. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Greene
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BayWa r.e Solar Projects LLC
Utility
CHGE
Entity
NYISO
Service Type
—
Point of Interconnection
North Catskill -Churchtown 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NORTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about North Catskill DG LLC