Russet Ridge Wind
119.1 MW generation in Steuben, NY · In queue since August 2024 · Proposed COD December 2029
119.1 MW
Capacity
1
Components
Wind
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Russet Ridge Wind project is a proposed 119.1 MW wind generation project located in Steuben County, New York. Developed by Liberty Renewables Inc., the project is interconnected to the NYSEG utility and is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-051. The project entered the queue on August 1, 2024, with a proposed commercial operation date of December 1, 2029.
The point of interconnection for the Russet Ridge Wind project is the Meyer-Eelpot 115 kV line.
Generated from interconnection queue and public data sources
State
NY
County
Steuben
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Liberty Renewables Inc.
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Meyer-Eelpot 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Russet Ridge Wind