Hemlock Hollow Wind
95 MW generation in Cattaraugus, NY · In queue since August 2024 · Proposed COD September 2029
95 MW
Capacity
1
Components
Wind
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
The Hemlock Hollow Wind project is a proposed 95 MW wind generation facility in Cattaraugus County, New York. Developed by Liberty Renewables Inc., the project is interconnected to the NYISO grid under queue ID NYISO-C24-052-001. The project entered the interconnection queue on August 1, 2024, with a proposed commercial operation date of September 1, 2029.
The proposed project is actively listed in the NYISO interconnection queue. Recent news coverage has discussed the project within the context of the energy industry.
Generated from interconnection queue and public data sources
State
NY
County
Cattaraugus
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Liberty Renewables Inc.
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Dugan - Homer Hill 115kV, Line #155
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Hemlock Hollow Wind