Highland BESS (NYISO-C24-057) — Project Summary

Queue ID
NYISO-C24-057
Capacity
79 MW
Technology
Battery
Status
active
Location
Orange, NY
Region
NYISO
Developer
Empire Reserve Energy, LLC
IA Status

Highland BESS

NYISO-C24-057BetaActiveBatteryNYISOLBNL

79 MW storage in Orange, NY · In queue since August 2024 · Proposed COD June 2029

79 MW

Capacity

1

Components

Battery

1y 9m

In Queue

IA Status

COD target: 2029

Status
Latest milestonecommissioningSolar Power World · 2025-02-04
Interconnection

Total Duration

4y 10m

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-06-01

About

Highland BESS is a proposed 79 MW battery storage project located in Orange County, New York. Developed by Empire Reserve Energy, LLC, the project is interconnected to the Orange and Rockland (O&R) utility grid at the Sugarloaf 138kV point of interconnection. The project entered the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-C24-057 on August 1, 2024, with a proposed commercial operation date of June 1, 2029.

The Highland BESS project consists of 79 MW of battery storage capacity. This development has been featured in recent news coverage related to industry and development.

Generated from interconnection queue and public data sources

Project Details

State

NY

County

Orange

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Empire Reserve Energy, LLC

Utility

O&R

Entity

NYISO

Service Type

Point of Interconnection

Sugarloaf 138kV

Data Source

LBNL

DeveloperCalibrant EnergySolar Power World · 2025-02-04
EPC contractorCS EnergySolar Power World · 2025-02-04
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE G
Hub Confidence
HIGH
Nearest Node (Estimated)
SUGRLOAF_69_KV_LOAD_REV_LBMP_G
POI Substation
Sugarloaf Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Highland BESS