Fraser Energy Storage
135 MW storage in Delaware, NY · In queue since August 2024 · Proposed COD October 2028
135 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The proposed Fraser Energy Storage project is a 135 MW battery storage development in Delaware County, New York. Developed by EDF Renewables Development, Inc., the project consists of 135 MW of battery capacity. It is located in the New York Independent System Operator (NYISO) queue as entry NYISO-C24-064, with a queue entry date of August 1, 2024, and a proposed commercial operation date of October 1, 2028.
The project is slated to interconnect at the Fraser substation 115 kV and is currently listed as active in the interconnection queue. Recent news coverage has discussed the project's potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
NY
County
Delaware
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Fraser substation 115 kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- HIGH
- POI Substation
- Fraser Substation