Springbrooke
82.8 MW generation in Genesee, NY · In queue since August 2024 · Proposed COD December 2029
82.8 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
The Springbrooke project is a proposed 82.8 MW solar generation project located in Genesee County, New York. Developed by SUNXI LLC, the project is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-076, with a queue entry date of August 5, 2024. The proposed commercial operation date is December 1, 2029.
The project is interconnecting to the Southeast Batavia-Golah Line 119. As of the current data, the project's interconnection agreement (IA) status is not specified. The project is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Genesee
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SUNXI LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Southeast Batavia-Golah Line 119
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Springbrooke