Maple Harvest Wind
162 MW generation in Onondaga, NY · In queue since August 2024 · Proposed COD December 2028
162 MW
Capacity
1
Components
Wind
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The Maple Harvest Wind project is a proposed 162 MW wind generation facility in Onondaga County, New York. The project, being developed by Maple Harvest Wind, is located within the NYISO region and interconnected to the Tilden-Cortland Line 18. It entered the NYISO interconnection queue as project NYISO-C24-079 on August 8, 2024, with a proposed commercial operation date of December 1, 2028.
The Maple Harvest Wind project is currently listed as active in the interconnection queue. Recent news coverage indicates industry interest in the development.
Generated from interconnection queue and public data sources
State
NY
County
Onondaga
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Maple Harvest Wind
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Tilden-Cortland Line 18.
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Maple Harvest Wind