BPP NY Somerset BESS I LLC
199.5 MW storage in Niagara, NY · In queue since August 2024 · Proposed COD March 2027
199.5 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
BPP NY Somerset BESS I LLC is a proposed 199.5 MW battery storage project located in Niagara County, New York. The project, developed by BPP NY Somerset BESS I LLC, is interconnected to the NYISO grid at the Kintigh 345kV point of interconnection. It entered the NYISO interconnection queue as project number NYISO-C24-091 on August 19, 2024, and has a proposed commercial operation date of March 1, 2027.
The proposed project consists of 199.5 MW of battery storage capacity. It is currently listed as active in the NYISO interconnection queue. Recent news coverage has discussed the project's progress and potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
NY
County
Niagara
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BPP NY Somerset BESS I LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Kintigh 345kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.