Basecamp BESS
170 MW storage in Chautauqua, NY · In queue since August 2024 · Proposed COD December 2027
170 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Basecamp BESS is a proposed 170 MW battery storage project located in Chautauqua County, New York. The project, developed by RWE Solar Development, LLC, is interconnected within the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-097. The project entered the queue on August 26, 2024, with a proposed commercial operation date of December 1, 2027.
The project consists of 170 MW of battery storage capacity. It is listed as active in the interconnection queue and has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Laona Station 115kV
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- HIGH
- POI Substation
- Avon Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Basecamp BESS