ELP Rotterdam Solar
35 MW hybrid in Schenectady, NY · In queue since August 2024 · Proposed COD July 2028
35 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The ELP Rotterdam Solar project is a proposed 35 MW hybrid solar and battery energy storage project located in Schenectady County, New York. The project, developed by ELP Rotterdam Solar LLC, consists of 35 MW of solar generation. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-102, with a queue entry date of August 27, 2024, and a proposed commercial operation date of July 1, 2028.
The point of interconnection for the project is the Rotterdam-Maple Ave 115kV Line 10. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Schenectady
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ELP Rotterdam Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Rotterdam-Maple Ave 115kV Line 10.
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.