NY125C - Little Salmon Solar
200 MW generation in Franklin, NY · In queue since August 2024 · Proposed COD December 2028
200 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
The proposed NY125C - Little Salmon Solar project is a 200 MW solar generation facility in Franklin County, New York. Developed by Boralex US Development LLC, the project is interconnected to the NYISO grid via the 345kV Line HW1 Haverstock - Willis.
The project entered the NYISO interconnection queue as queue ID NYISO-C24-108 on August 29, 2024. Its proposed commercial operation date is December 1, 2028. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Franklin
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Boralex US Development LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
345kV Line HW1 Haverstock - WIllis
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about NY125C - Little Salmon Solar