Falls Park Energy Storage
100 MW storage in Columbia, NY · In queue since August 2024 · Proposed COD June 2030
100 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
Falls Park Energy Storage, LLC is proposing a 100 MW battery storage project in Columbia County, New York. The project, identified as NYISO-C24-109 in the New York Independent System Operator (NYISO) interconnection queue, entered the queue on August 29, 2024. The proposed commercial operation date is June 1, 2030. The point of interconnection is the FALLS PARK 115 kV substation, served by New York State Electric and Gas (NYSEG).
The Falls Park Energy Storage project has been featured in recent news coverage related to development and deals. The project is currently listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Columbia
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Falls Park Energy Storage Project, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
FALLS PARK 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26