Fort Edward Solar Farm (NY53)
100 MW generation in Washington, NY · In queue since August 2024 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
The Fort Edward Solar Farm (NY53) is a proposed 100 MW solar generation project located in Washington County, New York. Developed by Fort Edward Solar LLC, the project consists of 100 MW of solar photovoltaic generation. It is listed in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-C24-111, with an entry date of August 29, 2024. The proposed commercial operation date is December 1, 2027.
The point of interconnection (POI) is the National Grid 115 kV Line #15 from Mohican to Battenkill. The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
NY
County
Washington
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Fort Edward Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
National Grid 115 kV Line #15 from Mohican to Battenkill
Data Source
LBNL + Live
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.