Iris Bloom Solar
150 MW hybrid in Chautauqua, NY · In queue since August 2024 · Proposed COD June 2030
150 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
The Iris Bloom Solar project is a proposed 150 MW hybrid solar and battery energy storage project located in Chautauqua County, New York. Developed by Iris Bloom Solar Project, LLC, it consists of 150 MW of solar photovoltaic generation. The project is currently active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-C24-115, with an entry date of August 30, 2024.
The proposed commercial operation date for the Iris Bloom Solar project is June 1, 2030. The point of interconnection is the Moon Road Sub 115 kV substation.
Generated from interconnection queue and public data sources
State
NY
County
Chautauqua
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Iris Bloom Solar Project, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Moon Road Sub 115 kV
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Iris Bloom Solar