Field Day Solar
300 MW hybrid in Oneida, NY · In queue since September 2024 · Proposed COD June 2030
300 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
Field Day Solar is a proposed 300 MW hybrid solar and battery energy storage project located in Oneida County, New York. The project, developed by Field Day Solar Project, LLC, consists of 300 MW of solar generation. It is listed in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-120, with a queue entry date of September 3, 2024, and a proposed commercial operation date of June 1, 2030. The point of interconnection is the Boonville to Rome 115KV Line 3.
The Field Day Solar project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NY
County
Oneida
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Field Day Solar Project, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Boonville to Rome 115KV Line 3
Data Source
LBNL
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Field Day Solar